A wry “master” unprofessionally flooded the floor of Horizon Eunice: pits, mounds. Poured over the eye, not using the level. The parquet workers rejected everything; we cannot continue further repairs. What is the way out?

Tatyana.

Expert Answer

Tatyana!

To get out of this situation, you can use two proven methods. If the height allows, then over the defective surface it is possible to fill with the same material. Its thickness should be such as to make it horizontal along the highest point of the bulk floor. The poured material is distributed on the surface with a needle roller and must be aligned with the rule.

In the case when there is no way to increase the thickness of the floor, you will have more painstaking work. First, you need to remove the hillocks and hills on a flooded surface. To do this, you can use a grinder or a manual grinding tool. In this case, they necessarily use the rule, which repeatedly check the level of repaired plots. Next, the floor should be thoroughly cleaned and the recesses and bumps should be leveled with a spatula. For these purposes, you can use the same mixture that was used for the first time (kneading a denser composition) or polymer putty of any brand. Since your self-leveling floor is not front, you can finish the repair and start laying the parquet.

Add a comment

 

Warm floor

Baseboard

Design